Jump to content

Lakegeneve

Member
  • Posts

    1,990
  • Joined

  • Last visited

Posts posted by Lakegeneve

  1. 2 hours ago, blackcab said:

    Just to make it really clear, you previously had to descend to street level and walk to the MRT as there was no physical connection linking the two stations.

     

    This has changed. Several years ago a direct covered link bridge/walkway was added to connect both stations.

    The pedestrian link cost US$3m to build and opened in mid 2013,some 3 years after the ARL opened! It has been a very, long time since anyone had to cross at street level to the MRT.

     

    These links used to be an after thought,eg. BTS to MRT at Asoke opened 1 yr after and BTS to MRT at Silom 2 yrs later. Thankfully, these days they are being built when new lines are bult.

    • Thanks 1
  2. 2 hours ago, tomazbodner said:

    Ratchaprarop is one way most of the time. So he should get off at Phyathai to go south, while Ratchaprarop is good going north. For taxi it's hard to make a right-turn so close to station.

    2 hours ago, Lakegeneve said:

    (Private vehicles are not allowed to use the soutbound bus lane but taxis usuaully can and do)  Again, don't do this at peak times.

    Ratchaprarop has a single bus southbound lane 24/7. However, taxis are also allowedto use it though it is no uncommon for private vehicles to sneak allow as well - they are allowed late at night. And there is no right turn, you simply exit the ARL station at the east exit which is on the east side of Ratchprarop rd and walk 30m south across the SRT eastern line and Makkasan rd. Grab a taxi there outside Verve condo or a little further along at the corner of soi 8 (one way, west) as taxis tend to exit from there.

     

    The reason why you don't want to do this at peak is that buses back up at Pratunam intersection (Petchaburi rd) along the single lane and you could literally spend 20-25 mins travelling the 1km south to Ratchaprasong intersection- the literal center of Thailand.

  3. A couple issues depend on how you can traverse this. The most important is your fitness for carrying your 2 heavy backpacks. It is about a 300m total transfer distance between the ARL & MRT via the pedestrian link and normally easy with a trolley bag.

     

    The other main factor is the time of day when you will be travelling, ie peak hour or not? I'd avoid doing it at peak hour as the MRT is very full - if morning peak up until 9.30am then forget about it as pax are crammed and it is normal to wait 1-2 trains to board. It will be very tough with 2 large backpacks.

     

    Another option is to alight at ARL Ratchprarop station and just take a taxi straight south down Ratchaprarop rd to Lumpini/Rama4 intersection if it is a quieter time of the day. (Private vehicles are not allowed to use the soutbound bus lane but taxis usuaully can and do)  Again, don't do this at peak times.

    • Like 2
  4. On 11/28/2022 at 9:04 AM, it is what it is said:

     

     

    I know. I know all the arguments against these great old beasts, but similar to the routemaster in london, i've ridden these iconic buses for years, they're part of my history and, for me, part of bangkok. i'll miss the wooden floored, fume spouting old girls...

    DSCF0566.JPG

    These buses will still be around for a number of years even though the BMTA is attempting to replace much of the fleet. The BMTA has asked the govt to provide funds to update the fleet for around 12 years now Including a request for 5000 new aircon and non aircon buses after the junta came to power. At any given time around 800 buses are out of action due to age & maintenence issues) All that has been funded was the 490 NGV Bestlin buses a few years ago, but there is obviously a push to electrify the fleet.

     

    As fares are charged according to the quality of the bus, the non-aircon buses are the cheapest (8 baht) for the poor,  min half the fare of a new NGV Bestlin bus (15-20-25 baht).

     

    It is one of the crazy and confusing aspects of BKK buses for tourists. You can have 4 different types of buses with the same route number (BMTA non-Aircon, BMTA aircon, private operator non-aircon, private operator aircon) all with completely different fare structures. 

    • Like 1
  5. Quote

    From January next year, all commercial trains will switch from the old Bangkok station of Hua Lamphong to Bang Sue,

    Poor reporting by Thai PBS who normally do a good job. This is incorrect as Eastern lines services will still continue to operate from HL as will suburban services for at least the next 5 years.

    A few ordinary (the really slow ones) inter-city services will also continue to operate from HL too,

    • Like 1
    • Thanks 1
  6. On 11/22/2022 at 1:28 PM, digbeth said:

    yesterday BTS post a video moaning about the unpaid debt by BMA, looks like the current Bangkok administration realize they bit off more than they can chew when they had a look at what contract were signed between BMA and BTS

     

    even if they manage to nationalize and transfer control of green line to MRTA, BTS will still be around to operate the monorails, plus AERA1 contract for the Airport/High speed link is another 50 years.

     

    looks like Bangkok will have integrated operator a la transport for London when hell freezes over

    A couple of things. BTSC will still have the concession for the BTS lines until 2029 even if the BMA transfers ownership o f both BTS lines to the MRTA. Don't forget that much of the unpaid debt issue relates to the fact that the MRTA did both the Keha (Suk line south ext) and Khu Khot exts (Suk line north ext) and then transferred the debt to the BMA which subseqently contracted the BTSC to run the exts while also having very lengthy free fare periods for both exts.

     

    For AERA1 (Aka 3 Airport line) the CP consortium consists of BEM amongst others. I didn't think that the BTSC were involved?

     

    A common ticketing platform for the whole network remains as eleusive as the end of corruption in Thailand....The MRTA could have made it compulsory with all recent tenders (Orange, Pink & Yellow. & Purple ext to come), but did not.

    • Like 1
  7. On 11/16/2022 at 7:00 AM, burner2014 said:

    @Lakegenevecatching up a bit on our discussion we had the last 2 years. 

    Study is done and now waiting for cabinet approval. You were right it takes a long time haha 2029 is planned so 2030 or so is realistic for this new line https://www.railjournal.com/passenger/light-rail/bangkoks-bang-na-suvarnabhumi-lrt-feasibility-study-completed/


    Living in the area around that line I still think this line will be used a lot especially because it will connect the airport in the last phase.


    Wiki Overview: https://en.wikipedia.org/wiki/Bang_Na–Suvarnabhumi_light_rail

    BMA isn't planning to tender the line for another 2 years. However, similar to the update I did above on 10 Sept for the BMA Grey line, the BMA Gov wants the MRTA to take on this project. If they do, this will lead to more delays with the current process as the MRTA has other priorities first with the MRT Purple line ext and MRT Brown line. Most likely the Grey line would also be a priority before this line too. 

     

    We'll have to wait and see if the MRTA decides to take on both projects. 

    • Like 1
  8. On 11/18/2022 at 6:23 AM, Hugh Cow said:

    when is the wan wian yai to mahachai line going through? I heard it was being delayed. I like the old SRT train anyway so the longer the skytrain is delayed the better.

    No real difference to the reply that I wrote on 6 July to your previous similar query. "Thus, the Hualamphong to WWY to Mahachai section won't be done for many years. I had hoped that the full southern ext would be done by 2030, but realistically the section you are asking about probably won't be done until the mid 30s now."

     

    The next stages of the SRT Red lines exts are currently planned to be tendered in Feb 2023;

     

    1) SRT Dark Red line north ext Rangsit to Thammasat Uni : aim to sign contract in May

    2) SRT Dark red line south ext Bang Sue to Hualumphong: contract in Sept

    3) SRT Light Red line west ext Taling Chan to Salaya: aim to sign contract in June

    5) SRT Light Red line east ext Bang Sue to Hua Mark: contract in Sept

    Note: expect these dates to change.

     

    Also, note that the trench past the palace that needs to be built for (2) & (5) also has to include the ARL ext which will start work soon.

    spacer.png

     

    • Like 1
  9. On 11/8/2022 at 11:02 PM, ThoMichael said:

    Had nothing to do with saving 50 baht, or whatever it would be... ???? 

     

    Yeah, it was the old school train. It is a direct line from Hua Lamphong to LakSi. Taking the MRT you have to change from red train to blue line, so taking one train just sounded fine to me. I just like old trains. I once took the old train from Saigon to Hanoi Vietnam. Not a single foreigner on the train, but I liked it. 

     

    Have a good night. 

    I can understand you wanting to take one of the diesel commuter services from HL to Laksi. Not that I'd do it myself for this trip. However, I think the lesson here as with most trips in BKK is to always have a Plan B. At a certain point (after15mins waiting?) I would have ditched the SRT commuter train and just used the MRT Blue Line and SRT Dark Red line to Laksi. 

     

    The 40 mins that you spent waiting on the train is nearly the total trip time from HL to Laksi. Alternatively, MRT to Chatuchack station and then a bus straight north up Vihavadi-Rangsit rd would actually be quicker.

     

    Posting the network map for those who might be unsure of the SRT Dark Red line route and how to connect. 

    spacer.png

    • Like 1
  10. On 9/10/2022 at 5:54 PM, Lakegeneve said:

    Construction progress as at 31 August:

    1) MRT Orange Line: 96.38%

    2) MRT Pink Line: 92.27%

    3) MRT Yellow Line: 96.05%

    4) MRT Purple Line (southern ext): preliminary site prep works underway

     

    New MRT Orange Line opening date - August 2025!

    Although Orange Line construction will essentially be completed by the end of the year, the previous opening date of March 2024 has now been pushed back to August 2025! This is due to the debacle of the cancelled and much delayed Orange Line western extension PPP tender. Whoever, wins that tender also wins the right to operate the Orange line eastern section AND has to order rolling stock which normally take 2 yrs to deliver from order.

     

    The tender will be awarded in Dec if there are no further delays. There are two bidders (BEM/Karnchang & ITD/IncheonMass Transit) as the BTSC boycotted the process. The successful bidder will need to order rolling stock promptly early in 2023 as not only does it take 2 yrs to deliver, but the line will require 3-5 months of full testing once sets are delivered. That Aug 2025 could thus slip to later in 2025......

     

    Had the MRTA done the operations & rolling stock tenders for the Eastern section in early 2021, then we could've been looking at a mid 2023 opening date! When construction commenced in June 2017, with a 1080 day construction period, the original opening date was Oct 2022.

    Construction progress as at 31 October:

    1) MRT Orange Line: 98.31%

    2) MRT Pink Line: 93.29%

    2a) Pink Line Spur to MTT: 8.08%

    3) MRT Yellow Line: 97.36%

    4) MRT Purple Line (southern ext): 3.75%

     

    MRT Orange Line western extension tender - 13.4k, 11 stations

    BEM/Karnchang has won the tender for the western extension. Barring further litigation from the BTSC, the contract should be signed early next year with work starting by mid year. 

     

    spacer.png

    • Like 1
    • Thanks 1
  11. On 10/22/2022 at 5:57 PM, khunjeff said:

    Anyone who has gone past either of these lines knows that these have to be partial openings, so I can't understand why none of the press coverage mentions this. Each time that opening dates were announced in the past (they all went by the wayside), the government made specific mention of exactly which stations would be serviced in the beginning and which would open later. 

    Orignal partial opening date was Oct last year which became June this year and then September and now is Jan 2023.

     

    The BSR (owner & operator) has been doing some full line test runs for the MRTA Yellow line in the last 3 weeks. The headline is misleading as there are only some special ticketed runs planned for December at this stage.

     

    The actual opening for is not planned until January with a free period, probably later in the month and only from Phawana (Y2) to Samrong ie. not Latphrao station. (The previous opening plan for last year and mid this year was for the more advanced southern section of a line from Samrong to Hua Mark)

     

    For the MRTA Pink Line, it is planned to open the first section in Feb or more likely March. The 1st stage opening will run from Minburi to the Govt Complex. (except for two stations). Mid year the 2nd stage willopen from Govt complex to Tiwanon rd.

     

    The last stage to Nonthaburi Provicial office will open in around 1 year as the station site had to moved 350m east due to supposedly blocking the views of the provincial office staff. 

     

    In other news the MRTA Orange line construction will be completed by the end of this year/very early 2023. Unfortunately, the MRTA stuffed up the tender to operate that line and order rolling stock - it is still not done - so you'll need to wait until June 2025 to use it!!

     

    MRTA Purple line southern ext started construction 3 months ago as is around 3.5% advanced

    spacer.png

    • Thanks 2
  12. On 9/30/2022 at 8:56 AM, allane said:

    Can you clarify this re the four quadrants of the Victory Monument bus stops; the NE quadrant, the SE quadrant, the SW quadrant and the NW quadrant.  Normally buses stop at the last quadrant before they leave the Victory Monument circle.

     

    166 departs from the NW quadrant from the east side 'platform'. It heads straight onto the expressway entrance just north of VM. The bus exits at Chaeng Wattana rd, runs west to Pak Kret, does a U-turn and then returns east along Chaneng Wattana before turning left into CW-Pak Kret soi 33 to enter into MTT.  I've used it loads of times over the years to go to Koh Kret.  Inbound and outbound are mostly exactly the same route. It can be confusing on CW rd if you don't read thai as both VM & MTT bound services run along here. Only the dark blue aircon buses run to MTT.

     

    Download the VIa Bus app if you haven't done so as it shows routes for every BMTA bus. I had no idea of the route to Govt Complex, but I have seen the 166 bus outside. According to the VIA Bus app it exits the expressway straight east onto CW rd and then turns into the Govt Complex rd.

     

    Obviously, just ask the conductor at VM if unsure if it is a MMT or a Govt Complex bus.

  13. There was a small female only (driver & pax) taxi company that started about 5 years ago. However, they didn't survive Covid. Not sure if they have or will been revived? All Taxi Thai - book bby app - with the distinct yellow taxis was a safer company to use prior to Covid, but haven't seen many of their taxis around.

     

    There are a few Lady Taxi driver services on FB and the web but mainly for out of BKK trips. Can contact them to ask if you needed a regular service.

     

    You can request a "Lady" driver with Grab, https://www.grabdriverth.com/service/gc-lady

    • Like 1
  14. The ASC courts above Foodland in Suk soi 16 are indeed the place to play. I have a few friends that play there weekly. I've only casually played a couple of times as I play volleyball there.

     

    I would suggest getting to know the fit women who run ASC and challenging them to a game one evening, they play regularly when they are bored. Let them know you are looking to play with others & go from there, eventually you'll be invited to join others.

  15. On 3/20/2022 at 10:53 AM, Lakegeneve said:

    The feasibility study and a draft EIA have been completed for the BMA Grey line. The BMA held a consultation meeting with the private sector on Thursday to provide an overview of this PPP tender. Detailed designs are planned to be completed by early 2023 and thereafter will seek Cabinet approval by around mid year. Still not planning to do the tender until 2024.....

     

    There's a video in the previous post if you want to view the comnplete, potential line.

    spacer.png

    BMA Grey Line update

    No change to the timeframe for the Grey Line. The main news is that the new BMA Gov has stated that he is inclined to transfer the Grey Line project back to the MRTA for better integration with the MRT network and due to the ongoing debt to BTSC which is his main priority.

     

    If this does happen, then it will delay the project further and the MRTA priorities are the Orange Line western ext and the MRT Brown line. However, one of the advantages of the MRTA doing both the Brown and Grey lines is that an integrated depot could be built for both lines. The BMA has secured a depot site whereas the MRTA has not, Such an outcome could also allow the possibility of operational flexibility with Grey line trains partially running on the Brown line and vice versa. eg, during peak hour you could have every 3rd train run from Thonglor to the Brown line terminus at NCC & return. Not ideal for slow monorail track turnouts, but still possible.

    • Like 1
    • Thanks 1
  16. On 7/11/2022 at 11:43 AM, Lakegeneve said:

    Construction progress as at 30 June:

    1) MRT Orange Line: 95.31%

    2) MRT Pink Line: 91.01%

    3) MRT Yellow Line: 94.18%

    4) MRT Purple Line (southern ext): preliminary site prep works underway

    Construction progress as at 31 August:

    1) MRT Orange Line: 96.38%

    2) MRT Pink Line: 92.27%

    3) MRT Yellow Line: 96.05%

    4) MRT Purple Line (southern ext): preliminary site prep works underway

     

    New MRT Orange Line opening date - August 2025!

    Although Orange Line construction will essentially be completed by the end of the year, the previous opening date of March 2024 has now been pushed back to August 2025! This is due to the debacle of the cancelled and much delayed Orange Line western extension PPP tender. Whoever, wins that tender also wins the right to operate the Orange line eastern section AND has to order rolling stock which normally take 2 yrs to deliver from order.

     

    The tender will be awarded in Dec if there are no further delays. There are two bidders (BEM/Karnchang & ITD/IncheonMass Transit) as the BTSC boycotted the process. The successful bidder will need to order rolling stock promptly early in 2023 as not only does it take 2 yrs to deliver, but the line will require 3-5 months of full testing once sets are delivered. That Aug 2025 could thus slip to later in 2025......

     

    Had the MRTA done the operations & rolling stock tenders for the Eastern section in early 2021, then we could've been looking at a mid 2023 opening date! When construction commenced in June 2017, with a 1080 day construction period, the original opening date was Oct 2022.

    • Thanks 1
  17. On 7/6/2022 at 1:56 PM, Lakegeneve said:

    It was announced by the consortium 2 months ago that the ARL ext to DMK (1st stage of the Eastern HSR) would start construction by Sept, but I'm not seeing much happening on that front right now.

    It was announced yesterday that construction would start in October. Reportedly, all land has been handed over, but I highly doubt that claim.

     

    Quote

     

    Kanit said the EEC was told that the State Railway of Thailand (SRT) has completed the expropriation of land for the project and the areas have been handed over to the contractor – a CP-led consortium called AERA1.

     

    He added that the contractor has moved into the construction sites to start preparations, such as building roads and factories for making pre-fabricated parts of the railway. The actual construction is expected to start in October.

     

    https://www.nationthailand.com/in-focus/40017608

    • Thanks 1
×
×
  • Create New...