So my latest update. Produced 1.177GBh. The Grid Smart meter has not arrived yet as promised from Korat!! Covid an easy out for the delay.. It only took PEA Nang Rong however 1 week to replace my meter which spun backwards with another one that did not and then charged 500bht!!!. . There was 2 grid losses through the month 4 hours and 5 hours. The second outage looks like when power was returned it spiked the readouts with false info. As a result on the 13th our consumption/production was over the top. I'm trying to get the contractors to amend the glitch. They have more access than me to the platform so maybe they can alter the it. The graph does not show but I probably exported to PEA around 700Kwh free. Even the antacid tablets are not stopping that feeling of being eaten from the inside out! The bin for the month was 2,667Bht 698Kwh consumed.
The plant is also coming up for its first 6 month service and again Covid is going to put that on hold I'm sure. There is an issue with the RCBO breaker tripping (see below) in moderate to heavy rain. I'm presuming it is tripping due to an earth problem and not over current as the solar panels are producing <deleted> all at the time. Easy to fix resetting the breaker but pain in the @rse having to do so. I'm thinking of getting a hose on the exposed wiring which is in mostly in conduit and seeing if I can trip the breaker??
Have done heaps of research on batteries.. I was looking in all the wrong places... I have found a supplier in Thailand that sells Huawei genuine batteries which will click and play. I have not discounted going down this path yet... A 15kwh Lithium system 297,712Bht. I will follow up with another post later.