mascarabertha Posted December 27, 2014 Share Posted December 27, 2014 I have a new construction company working for me. They are 30 days into demolition and about to start construction. Daily I get a report with photos, whether or not they've reached their daily goal, what materials are on site, how many workers were present e.g. 1 forman, 1 architect, 4 plasterers. They are young, speak perfect English. Many are on the faculty at CMU. At the daily report What % of the final goal that they've achieved. I've never experienced anything like this anyplace. They are innovative, well connected, have built hotels in the area as well as a sterile building for Apple computer to construct some gizmos 1 Link to comment Share on other sites More sharing options...
CMKiwi Posted December 27, 2014 Share Posted December 27, 2014 As Monty Pythons Life of Brian had quoted..."You lucky, lucky bastard" I just hope that no one steals your workers before they finish your job. Link to comment Share on other sites More sharing options...
DLock Posted December 27, 2014 Share Posted December 27, 2014 Is this Apple building in CM? Sounds like a good company. Hope the end results is as good as the process. Pictures of the building once you have something interesting to see are always welcomed. Good luck. Link to comment Share on other sites More sharing options...
arunsakda Posted December 27, 2014 Share Posted December 27, 2014 Are they able to install high spec casement style windows? Link to comment Share on other sites More sharing options...
quidnunc Posted December 27, 2014 Share Posted December 27, 2014 Can you share the contact info for this company? Link to comment Share on other sites More sharing options...
worgeordie Posted December 27, 2014 Share Posted December 27, 2014 Do not understand why they should have 4 plasters on site,as you say demolition nearly finished,and about to start construction, plasters would not be required until the build is near completion, am i missing something here ? regards Worgeordie 1 Link to comment Share on other sites More sharing options...
Popular Post Dante99 Posted December 27, 2014 Popular Post Share Posted December 27, 2014 (edited) "They are young, speak perfect English. Many are on the faculty at CMU." Got to wonder about the facts reported if the above is an example. Perfect English is extremely rare at CMU outside a very few foreign earned PhDs in English who are in the English Department, not construction trades. How many CMU faculty types do you need to build a house? Surely they are not doing the real work. Daily goals are a bit extreme too. Apple?? Perhaps this paper slipped out of the how to clean your butt thread, subsection male buffalo. Edited December 27, 2014 by Dante99 3 Link to comment Share on other sites More sharing options...
Popular Post mamborobert Posted December 27, 2014 Popular Post Share Posted December 27, 2014 Richard...new nick I see......not banned again I hope. Three times now? 3 Link to comment Share on other sites More sharing options...
mariohh1 Posted December 27, 2014 Share Posted December 27, 2014 Can you sebd me the name and contact info please thanks Link to comment Share on other sites More sharing options...
elektrified Posted December 27, 2014 Share Posted December 27, 2014 Do not understand why they should have 4 plasters on site,as you say demolition nearly finished,and about to start construction, plasters would not be required until the build is near completion, am i missing something here ? regards Worgeordie I thought the same thing. Clearly he/she didn't get the 'story' straight before posting. Link to comment Share on other sites More sharing options...
Seligne2 Posted December 27, 2014 Share Posted December 27, 2014 While we are all happy for you, this post is completely gormless unless you divulge the name of the company. Link to comment Share on other sites More sharing options...
Phrafarang Posted December 27, 2014 Share Posted December 27, 2014 I would think you would have four plasterers because they can complete the same volume of work three times faster I believe that the Apple project the OP is talking about is probably the recently completed HANA Microelectronics factory in Lampun, a six hundred million baht factory to produce circuit boards for the new iphone. I know people at this company, if its the same one who built HANA's place, the Architects, Engineers and Designers are all taken from the top few percent of graduates and contrary to one posters suggestion they all speak pretty perfect English, they also have staff who speak French and German pretty well too. Link to comment Share on other sites More sharing options...
slapout Posted December 27, 2014 Share Posted December 27, 2014 Maybe the op is misspelling plasters and means ''blasters''. seeing is believing, sometimes.More info is needed as being a skeptic has saved mant a heart ache and a empty band account. Link to comment Share on other sites More sharing options...
Phrafarang Posted December 27, 2014 Share Posted December 27, 2014 Maybe the op is misspelling plasters and means ''blasters''. seeing is believing, sometimes.More info is needed as being a skeptic has saved mant a heart ache and a empty band account. I can see you are highly qualified in Cacography Link to comment Share on other sites More sharing options...
dutchisaan Posted December 27, 2014 Share Posted December 27, 2014 And what are you building? A Thai toilet? Sent from my iPad using Thaivisa Connect Thailand mobile app Link to comment Share on other sites More sharing options...
mascarabertha Posted December 27, 2014 Author Share Posted December 27, 2014 an example with photos of a daily work report Goal :1. REMOVE FLOOR TILE2. DETAIL CUTTING FOR WALL3. CLEAR CLEANING FOR THE SECOND FLOOR First shift : 8.00-12.00Climate : CLEAR SKYNO. of worker : 1 FOREMAN 3 WORKER Activities : WORKER CONTINUE TO REMOVE FLOOR TILE AT THE FIRST FLOOR. SOME WORKER DO DETAIL CUTTING FOR THE SECOND FLOOR. Second shift : 13.00-17.00Climate : CLEAR SKYNO. of worker : 1 FOREMAM / 5 WORKERS Activities : WORKER COMPLETED TO REMOVE FLOOR TILE AT THE FIRST FLOOR. SOME WORKER COMPLETED DETAIL CUTTING FOR THE SECOND FLOOR. AND CLEARING ALL AT THE SECOND FLOOR PROBLEM : NONE Material on Site : NONE NEXT DAY GOAL : (MONDAY) 1.CLEARING ALL FIRST FLOOR2. PREPARE FOR PLASTERING CEILING AT TH FIRST FLOOR 1 Link to comment Share on other sites More sharing options...
onthedarkside Posted December 27, 2014 Share Posted December 27, 2014 3 off topic posts removed. If members have nothing to contribute to the topic then read the next topic. Link to comment Share on other sites More sharing options...
ianf Posted December 27, 2014 Share Posted December 27, 2014 I know this company. It's run by a Mr Bill Der. Link to comment Share on other sites More sharing options...
sappersrest Posted December 27, 2014 Share Posted December 27, 2014 A typical extract from a UK site managers project diary, looks like you have struck gold, good luck with your project. Link to comment Share on other sites More sharing options...
mascarabertha Posted December 27, 2014 Author Share Posted December 27, 2014 Link to comment Share on other sites More sharing options...
Benjie Posted December 27, 2014 Share Posted December 27, 2014 So you joined a forum just to tell everyone how happy you are about using this company that you most definitely have no personal investment in? 2 Link to comment Share on other sites More sharing options...
SDH Posted December 28, 2014 Share Posted December 28, 2014 Okay I will bite, I'm looking a construction company right now, especially one that can work in Mae Hong Son - Please tell me their name and contact details. Link to comment Share on other sites More sharing options...
mascarabertha Posted December 28, 2014 Author Share Posted December 28, 2014 Okay I will bite, I'm looking a construction company right now, especially one that can work in Mae Hong Son - Please tell me their name and contact details. absolutely, send me a private inquiry Link to comment Share on other sites More sharing options...
ProThaiExpat Posted December 28, 2014 Share Posted December 28, 2014 What difference does daily reports make unless you are paying wages by the hour and materials by the item. The big change I have seen in the past few years is that contractors are now quoting the job as a whole and even their estimate of the breakdown between labor and materials is rarely accurate if even provided. Link to comment Share on other sites More sharing options...
mascarabertha Posted December 28, 2014 Author Share Posted December 28, 2014 Can you share the contact info for this company? are you doing a build? Link to comment Share on other sites More sharing options...
mascarabertha Posted December 28, 2014 Author Share Posted December 28, 2014 yesterday they sent up video drones Link to comment Share on other sites More sharing options...
Mooner Posted December 28, 2014 Share Posted December 28, 2014 For what? Bizarre. Link to comment Share on other sites More sharing options...
junglechef Posted December 28, 2014 Share Posted December 28, 2014 It's for show, don't you know here that form over function comes second only to loosing face 1 Link to comment Share on other sites More sharing options...
Phrafarang Posted December 29, 2014 Share Posted December 29, 2014 or maybe its so that you can inspect work they have carried out to your roof without having to climb up there yourself 1 Link to comment Share on other sites More sharing options...
zeichen Posted December 29, 2014 Share Posted December 29, 2014 Personally, I don't ever understand why anyone would pay 10k baht a day for these crews when the workers are locals making 300-500 a day. Foreman's making 7k baht a day seems a little steep. As long as you are satisfied with the quality, then pay what you want. I spent a long time getting a network of quality builders that charge reasonable prices. 10 years ago I built an addition to my house for 100k baht including everything. My friend hired a crew to do something similar and paid 350k baht. Both have stood up the test of time but now he uses my guys for everything. The only problem is now my guys are pushing 60-70 years old. Hard to find dependable crews that are younger. I also don't see why you would need any professors at all from engineering or architectural faculties. As for the comment about their English ability, get out more. There are several International programs where all the classes are taught in English. I know of at least 300 professors outside of humanities that communicate and comprehend English quite well. Link to comment Share on other sites More sharing options...