Skip to content
View in the app

A better way to browse. Learn more.

Thailand News and Discussion Forum | ASEANNOW

A full-screen app on your home screen with push notifications, badges and more.

To install this app on iOS and iPadOS
  1. Tap the Share icon in Safari
  2. Scroll the menu and tap Add to Home Screen.
  3. Tap Add in the top-right corner.
To install this app on Android
  1. Tap the 3-dot menu (⋮) in the top-right corner of the browser.
  2. Tap Add to Home screen or Install app.
  3. Confirm by tapping Install.

BMA governor inspects delayed Pattanakarn tunnel project

Featured Replies

BMA governor inspects delayed Pattanakarn tunnel project

By The Nation

 

5f5f7b0fa18fd768e2c6fab3397639ed1ee12eb268ec6f137f9d145d9670e954.jpg

Picture: Siam Rath

 

Bangkok Metropolitan Administration governor Aswin Kwanmuang on Wednesday inspected the long-delayed vehicle tunnel project on Pattanakarn Road.

 

After being assured that the Pattanakarn-Ramkhamhaeng-Thaworntrat project would be completed by its latest extended deadline of February next year, Aswin told the contractor to temporarily provide more space for traffic during rush hours from December 5.

 

He inspected the project after the BMA received complaints that the project delay was causing problems for motorists and local residents.

Pattanakarn Road has been suffering from traffic snarls and flooding after rains since the project started.

 

It was initially scheduled to be completed by April 10, 2018, and the deadline was extended to October 15, then extended again to February next year.

 

Aswin said he was told that the delay was caused by difficulties in relocating public utilities.

 

The delay was also attributed to the BMA changing the plan to provide more water storage for firefighting, if required, Aswin added.

 

Aswin said he also instructed the BMA's Drainage and Sewerage Department to prepare drain floodwaters from the road when there are heavy downpours.

 

Source: http://www.nationmultimedia.com/detail/breakingnews/30355300

 
thenation_logo.jpg
-- © Copyright The Nation 2018-09-27

And he said “yep, it’s delayed “

The completion date was extended to October this year about a year ago.  Now there are only a few days left and all they have to show is a little bit of excavation filled with muddy water.  Until recently all the contractor did was to close off parts of the road with concrete blocks to provide parking spaces for his vehicles. 

10 hours ago, webfact said:

The delay was also attributed to the BMA changing the plan to provide more water storage for firefighting, if required, Aswin added

Winnie the Pooh wouldn't even believe those lies. Envelopes have changed hands and all is forgiven. Until the next delay occurs and then more money needs to be forthcoming.

Thailand all over! 

Does anyone have a googleys map location for this tunnel?

Recently Browsing 0

  • No registered users viewing this page.

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.