thaidreaming Posted January 31, 2017 Share Posted January 31, 2017 My business consulting cannot help :) When you ask to MEA new power meter 200a 3-phase... Is a 200aX3 = 600total or just 66X3=200total? Thank you. Link to comment Share on other sites More sharing options...
Crossy Posted January 31, 2017 Share Posted January 31, 2017 You may not get a 200A meter, but if you do it will be 200A per phase. That's 132kVA, a LOT of juice, fair size factory? Certainly the biggest meter PEA will give without your own transformer is 100A 3-phase, MEA may be more generous. Link to comment Share on other sites More sharing options...