Pattaya announces 3-phase flood-mitigation project

image.png

PATTAYA:--Pattaya officials said they have a three-phase plan to reduce flooding on Beach Road, but although details were lacking for the 3rd phase.

 

Deputy Mayor Poramet Ngampichet met Oct. 25 with city engineers and sanitation staffers, Marine Department officials and the consultant to the ongoing Pattaya Beach restoration project.

 

The meeting was called in response to another disastrous rainy season in Pattaya where, unable to use existing pipes to drain water from Beach Road efficiently, the city demolished parts of the shoreline footpath to let water drain into the sea, cutting huge swaths out of a beach currently being rebuilt at the cost of more than a half-billion baht.

 

Poramet said the first urgent stage is to clean out all the pipes leading to the beach and manage the existing drainage system at critical points.

 

The second phase, he said, calls for improvement of the existing drainage system along Beach Road, including relatively new, wide and long pipelines at Soi 6/1 and near the old pier in South Pattaya.

 

Read more:http://www.pattayamail.com/news/pattaya-announces-3-phase-flood-mitigation-project-229310

 
pattaya_mail_logo.jpg
-- © Copyright Pattaya Mail 2018-11-02
  • Haha 1
Link to comment
Share on other sites

4 hours ago, Rimmer said:

Pattaya announces 3-phase flood mitigation project

Mitigation: the action to reduce the severity of something

ok.hmmmm

Phase1: after each flood wait 24 hours for the  water to drain naturally

Phase2: collect and remove all garbage floods brought in.

Phase3: All pray so next one isn't so bad

  • Like 1
Link to comment
Share on other sites

4 hours ago, Rimmer said:

The second phase, he said, calls for improvement of the existing drainage system along Beach Road, including relatively new, wide and long pipelines at Soi 6/1 and near the old pier in South Pattaya.

????

still waiting patiently for the announcement of the third one....

Let me run a wild guess. 3) import more sand!

Edited by pattayadude
Link to comment
Share on other sites

4 hours ago, Rimmer said:

Poramet said the first urgent stage is to clean out all the pipes leading to the beach and manage the existing drainage system at critical points.

 

The second phase, he said, calls for improvement of the existing drainage system along Beach Road, including relatively new, wide and long pipelines at Soi 6/1 and near the old pier in South Pattaya.

The third phase, Poramet said, would entail long-term development. No other details were forthcoming is to repeat announcing Phase 1 and Phase 2 at two or three year intervals.

Link to comment
Share on other sites

Should this not raise some (more) warning flags....

Quote

Old pipes will be linked with the newer, larger pipelines every 30 meters so that water moves through them at 0.6-3 meters per second. Any slower and sediment builds up and clogs pipes. Any faster and the pipes break.

The spec seems to have been a little lacking.............or not if you believe the brown envelope carousel scenario.........:shock1:

Link to comment
Share on other sites

45 minutes ago, mikebell said:

Phase 1 - appoint a committee to discover why water runs downhill.

Phase 2 - appoint a committee to reverse the above findings.

Phase 3 - all flood water now runs into Maprachan reservoir.

No thanks we don't need your Crap over here

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.










×
×
  • Create New...