More Phuket Town cables go underground


Recommended Posts

Posted

More Phuket Town cables go underground

Eakkapop Thongtub

 

1473066028_1-org.jpg

Work is carried out to remove the last high voltage power poles from Yaowarat Rd in Phuket Town. Photo: Eakkapop Thongtub

 

PHUKET:-- Work to put more of Phuket Town’s unsightly overhead cables underground were finally completed yesterday (Sept 4) 18 months after work started.

 

Boonrat Chareupong, Deputy Chief of Phuket Provincial Electricity Authority confirmed to The Phuket News today (Sept 5) that work on pulling down last three high voltage electricity poles on Yoawarat Rd was completed yesterday.

 

The most recent phase of the underground cable project on Yaowarat Rd started on March 2, 2015 and was expected to take at least 180 days to complete.


Full Story: http://www.thephuketnews.com/more-phuket-town-cables-go-underground-58980.php#lJl6cMiQIEmO0ECz.97

 
tphuketnews_logo.jpg
-- © Copyright Phuket News 2016-09-05

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...