BANGKOK: -- ACADEMICS said yesterday that the southern region would still have stable power generation in the near future even without the proposed Krabi coal-fired power plant, although Thailand would have to invest in some form of new power generation in the long term.

 

Meanwhile, the Office of Natural Resources and Environmental Policy and Planning (ONEP) sent an official letter to the Electricity Generating Authority of Thailand (Egat) on Monday asking the agency to comply with a prime ministerial order to conduct a new Environmental and Health Impact Assessment (EHIA) regarding the Krabi plant.

 

Decharut Sukkumnoed, a lecturer at the Faculty of Economics of Kasetsart University, said the southern region still had enough power to meet demand even though the coal-fired plant project had been halted by Prime Minister Prayut Chan-o-cha’s order regarding the EHIA.

 

“We have to understand that the power demand can be categorised into three types: the fundamental demand for average daily power usage, the daily maximum demand for the highest power consumption per day, and the annual peak for the highest power demand in a year,” Decharut said.

 

Source: http://www.nationmultimedia.com/news/national/30307562

 
thenation_logo.jpg
-- © Copyright The Nation 2017-03-01
Posted
4 hours ago, webfact said:

although Thailand would have to invest in some form of new power generation in the long term.

The developers have already offered to build a gas-fired power plant elsewhere as an alternative to the coal-fired power plant in Krabi. The issue sounds less one of energy supply than one of preset government corruption?

Posted

Some Hisos are obviously getting some very nice backhanders for these coal fired power stations,

 far more important than the environmental cost :bah:

Posted

Sorry the Krabi coal plant will be built one way or the other. Don't believed in Prayut cancellation of the EIA study will be the final death knell to the plant. His past broken promises evident of his untrustworthiness. The plant construction already awarded to a Chinese-Thai consortium and the coal supply will be from Banpu mines in Indonesia, Australia and Africa. Done deal and no turning back. Just watch the space.  

Posted
3 hours ago, Eric Loh said:

Sorry the Krabi coal plant will be built one way or the other. Don't believed in Prayut cancellation of the EIA study will be the final death knell to the plant. His past broken promises evident of his untrustworthiness. The plant construction already awarded to a Chinese-Thai consortium and the coal supply will be from Banpu mines in Indonesia, Australia and Africa. Done deal and no turning back. Just watch the space.  

No one should be in the least surprised if the word "submarine" was mentioned somewhere in small print in this Chinese/Thai contract.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...