Jump to content

Patong underground cabling works start next April


Recommended Posts

Posted

Patong underground cabling works start next April

The budget will be divided between the PEA, responsible for the cost of the electric system for 160 million Baht, and the Patong Municipality, responsible for the cost of the public works and new cable underground pits for 64 million Baht.

By Kritsada Mueanhawong

  

25346271_10155043723146516_1069742511_o-

 

Phuket’s Governor has received an update on the Patong underground cabling works during the morning meeting today (December 13).

 

Representatives from PEA (Phuket Electrical Authority), Patong PEA Office Manager, Watcharin Prapa, and Director of Undergrounding Project of PEA, Wachira Pitaktansakul, reported the progress on the targeted area, Taweewong Road (Beach Road), where a budget of 224 million Baht has been allocated.

 

The budget will be divided between the PEA, responsible for the cost of the electric system for 160 million Baht, and the Patong Municipality, responsible for the cost of the public works and new cable underground pits for 64 million Baht.

 

Full story: https://www.phuketgazette.net/news/patong-underground-cabling-works-start-next-april

 
pgazette_logo-20170817.jpg
-- © Copyright Phuket Gazette 2017-12-13

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...