Phuket light-rail budget B34.8bn for Phase 1 only, expected to jump 10%


rooster59

Recommended Posts

Phuket light-rail budget B34.8bn for Phase 1 only, expected to jump 10%

By The Phuket News

 

1561198009_1-org.jpg

Officials announced on Thursday (June 20) that the B34.8bn budget for the Phuket light-rail project is only for Phase 1 of the project and is likely to increase by 10%. Image: MRTA
 

PHUKET: The Mass Rapid Transit Authority of Thailand (MRTA) has revealed that the budget for Phase 1 of the Phuket light-rail project is likely to require a 10% increase.
 

However, MRTA’s Project Development Department Director, Gardphajon Udomdhammabhakdi, who was in Phuket on on Thursday (June 20) to deliver the news, has since confirmed to The Phuket News that the 10% increase would apply only to the budget for Phase 1 of the project, which he confirmed stood at B34.8 billion.

 

“Actually, we don’t know how much Phase 2 will cost,” Mr Gardphajon told The Phuket News.


Full story: https://www.thephuketnews.com/phuket-light-rail-budget-b34-8bn-for-phase-1-only-expected-to-jump-10-71886.php#dFuHrCOBCd35jwps.97

 

tphuketnews_logo.jpg

-- © Copyright Phuket News 2019-06-22

 

 

 

Link to comment
Share on other sites


14 hours ago, rooster59 said:

Phuket light-rail project is likely to require a 10% increase.

For phase one only.... wait till the first concrete has been poured then it will escalate into a few more digits!

Link to comment
Share on other sites

Just how they think that this system combined with motorcycles is going to work is fantasy. They limbo under level crossings & shift bollards when U-turns are banned for their safety. Don't get me started on the lowered/raised smoke billowing pick-ups that will need to be extricated from under/over the trains. Hope they come with 10 years free panelbeating included.

Link to comment
Share on other sites

15 hours ago, rooster59 said:

Phase 1 of the Phuket light-rail project is likely to require a 10% increase

TRANSLATION:

"Administrative Fee."

15 hours ago, rooster59 said:

we don’t know how much Phase 2 will cost,

TRANSLATION:

"Administrative Fee" not known yet.

Link to comment
Share on other sites

Mr Gardphajon said that the Ministry of Transport is not worried about the budget of the Phuket light-rail project as long as it is safe and does not interfere with traffic.

There is absolutely no way that this project could be undertaken without interference to traffic. We can probably expect to lose a lane of traffic on each side of Thepkasattri Road and that would probably be enough to cause gridlock on this already busy road.

 

 


 
  • Like 2
Link to comment
Share on other sites

16 hours ago, madmitch said:

Mr Gardphajon said that the Ministry of Transport is not worried about the budget of the Phuket light-rail project as long as it is safe and does not interfere with traffic.

There is absolutely no way that this project could be undertaken without interference to traffic. We can probably expect to lose a lane of traffic on each side of Thepkasattri Road and that would probably be enough to cause gridlock on this already busy road.

 

 


 

I know land aquisition can be a problem here, but, surely it would be easier to use the vacant land either side of the road for the majority of the planned route than to try to integrate the road and rail together.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.








×
×
  • Create New...