Jump to content

Superhighway Underpass Open


ihop

Recommended Posts

Was riding out to dinner last night heading north on the superhwy and all of a sudden I realize i'm going UNDER CharoenMuang Road and into the new underpass! No more bobbing and weaving and waiting at the intersection.

Both north and southbound underpasses were open to traffic last night. Never thought I'd see the day! Two more underpasses to go?

Link to comment
Share on other sites


Was riding out to dinner last night heading north on the superhwy and all of a sudden I realize i'm going UNDER CharoenMuang Road and into the new underpass! No more bobbing and weaving and waiting at the intersection.

Both north and southbound underpasses were open to traffic last night. Never thought I'd see the day! Two more underpasses to go?

hope they re-time the traffic lights for those "above ground", currently you wait up to 180 sec (3 minutes) per phase and thats if youre lucky to get thru the phase, <_<

Link to comment
Share on other sites

Two different contractors I'm afraid. The two remaining underpasses will be not be completed in the forseeable future but the work will move forward enough to allow normal cross traffic to flow again. One step forward and back three.

Link to comment
Share on other sites

Was riding out to dinner last night heading north on the superhwy and all of a sudden I realize i'm going UNDER CharoenMuang Road and into the new underpass! No more bobbing and weaving and waiting at the intersection.

Both north and southbound underpasses were open to traffic last night. Never thought I'd see the day! Two more underpasses to go?

Yup, two more to go, though especially the San Dek one just doesn't seem to be happening.

I still think it's ludicrous to have traffic lights on top of it; it now takes LONGER than before during construction when traffic just flowed around.

Now on to the next project. :o The flyover at the Third Ring and Superhighway #11 is coming along nicely as well.

So that just leaves under or over-passes of the Third Ring with the old Lamphun Road, and the Hang Dong road (Samoeng Intersection). (Don't care about any other intersections on that ring.. :D )

Something elevated and fancy to connect the Middle Ring with the Canal Road would be nice too; they're building a regular intersection & bridge now it seems. But really it would be nice to just fly over the Canal Road, then merge into it on a ramp similar to the Airport Plaza flyover.. That would mean some serious pillars in the water I suspect. Oh well, one day. :D

Link to comment
Share on other sites

The hole at Chang Puak has had more work done on it in the last two months than in the last three years. Hopefully they'll complete the job soon.

You are not wrong there! With the new crews, they seem to have accomplished more in the last few weeks, than the last year. All the cast beams for the Chotana/Mae Rin road have been done and some new ones are actually in place. Excavation continues at an awe inspiring pace, and I can see it being completed this side of Christmas, weather permitting :o

Link to comment
Share on other sites

Wow, that is good news. IMO, they did a fine and fast job at the Sankhampeang intersection.

Congratualations to the constructors.

It also won't be long before the bridge over the Superhighway at the 121 road will be open. Maybe the same constructor?

Great!

Nienke

Link to comment
Share on other sites

The two remaining underpasses will be not be completed in the forseeable future but the work will move forward enough to allow normal cross traffic to flow again.

How do you know that they don't intend to complete the underpasses ?

Edited by lamphun
Link to comment
Share on other sites

Didn't the minister for transport, or his no.2, inspect the halted road works a month or so ago, and promise that they would be finished within 6 months? By the sound of things he is sticking to his word!!! I feel that the Chotana/Mae Rin underpass has been a major eyesore and pain to navigate for the last 2 years or so, since it was started.

Link to comment
Share on other sites

The two remaining underpasses will be not be completed in the forseeable future but the work will move forward enough to allow normal cross traffic to flow again.

How do you know that they don't intend to complete the underpasses ?

I should have qualified my post by saying that the story came from a well connected Thai family here in Chiang Mai. Nothing more, so at the least it can be taken as rumor. I like everyone else hope it's not true and like everyone else hope they will complete both projects.

Link to comment
Share on other sites

The two remaining underpasses will be not be completed in the forseeable future but the work will move forward enough to allow normal cross traffic to flow again.

How do you know that they don't intend to complete the underpasses ?

I should have qualified my post by saying that the story came from a well connected Thai family here in Chiang Mai. Nothing more, so at the least it can be taken as rumor. I like everyone else hope it's not true and like everyone else hope they will complete both projects.

the newly erected sign (in thai) at san dek specifically indicates the start of the work as 1st june 2007 and completion date within 6 months. the work going on at this point of time seems to point that we should be able to use the underpass before the end of this year although we all know how long the project has been delayed.

Link to comment
Share on other sites

The two remaining underpasses will be not be completed in the forseeable future but the work will move forward enough to allow normal cross traffic to flow again.

How do you know that they don't intend to complete the underpasses ?

I should have qualified my post by saying that the story came from a well connected Thai family here in Chiang Mai. Nothing more, so at the least it can be taken as rumor. I like everyone else hope it's not true and like everyone else hope they will complete both projects.

the newly erected sign (in thai) at san dek specifically indicates the start of the work as 1st june 2007 and completion date within 6 months. the work going on at this point of time seems to point that we should be able to use the underpass before the end of this year although we all know how long the project has been delayed.

I also read in a Thai newspaper that the department of transportation has taken over the work from the old contractors because they ran out of money, and intended to finish the work within 6 months as there's not much work left.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.








×
×
  • Create New...