The construction of the Rama II Road expressway, currently plagued by delays, substandard work and safety concerns, has prompted Prime Minister Srettha Thavisin to consider downgrading contractors responsible for the project. The state budget office was instructed to investigate possible penalties for the contractors involved.

 

Patricia Mongkhonvanit, director-general of the Comptroller General’s Department, was called to meet with the prime minister on Monday to discuss the recurring issues. The department oversees the budgets of all state projects.

 

“The problems arising from the delays in the construction work on Rama II Road continue to have somewhat serious effects on people. They must be fixed,” PM Srettha stated following their meeting. He then left for Melbourne to attend the ASEAN-Australia summit.


Firms found to violate project deadlines or produce substandard work will be downgraded, he added. These punitive measures, he believes, will encourage contractors to be more attentive and responsible in their construction projects.


However, the Premier did not clarify whether the penalties would apply to both major contractors and subcontractors, or what the downgrading process entailed. Construction companies that win significant projects usually subcontract portions of the work to smaller firms.

 

Rama II Road is a primary connection between Bangkok and the southern region, including the popular resort town of Hua Hin. Traffic congestion on Rama II has been recognised by the current and previous governments as a detriment to tourism in the area. Local and international tourists opt for alternative destinations to avoid the traffic bottlenecks.

 

The expressway, designed to reduce travel time from Bangkok to Samut Sakhon, has in reality exacerbated congestion due to construction delays, frequent accidents, and road closures. The situation is particularly dire during weekends and long holidays.

 

Several construction mishaps have even led to fatalities. The most recent incident occurred on January 18, when a sling snapped, killing a worker and causing the crane’s lifting basket to plummet. In May, another worker was killed by a falling slab of concrete.

 

The construction of the new expressway is divided into ten separate contracts. It commenced in February 2012 and was initially set for completion in January next year. However, the main contractor has already been granted a six-month extension.

 

Transport Minister Suriya Jungrungreangkit assured on Monday that the expansion of Rama II Road would meet its new deadline, if not be completed ahead of schedule, with bi-monthly follow-ups, reported Bangkok Post.

 

by Mitch Connor

Photo courtesy of Bangkok Post

 

Source: The Thaiger 2024-03-05

 

- Cigna offers a range of visa-compliant plans that meet the minimum requirement of medical treatment, including COVID-19, up to THB 3m. For more information on all expat health insurance plans click here.

 

Get our Daily Newsletter - Click HERE to subscribe

 

Join us now!

Link to comment
Share on other sites

30 minutes ago, webfact said:

The construction of the new expressway is divided into ten separate contracts. It commenced in February 2012 and was initially set for completion in January next year. However, the main contractor has already been granted a six-month extension.

 

hahaha 6 months.

Link to comment
Share on other sites

This is one of the most ridiculous construction projects on earth. Though any sort of alternative transportation is desperately needed here, a project that takes 10-30 years (how long has it been under construction already? And they are only at km. 37, and completion is minimal to that point) on one of the most congested highways in the nation is sheer insanity, hubris, and poor planning. Heads should be rolling, and people should be locked up for this mess.  

  • Like 2
Link to comment
Share on other sites

  • Contractors and subcontractors and subsubcontractors.... every one wants to make money.. a lot is wasted and with the result delays, low standard works and a lot of traffic congestion... yes indeed they can't fix in a few months anymore surely after many years they are building at the site. I think another 3 years are needed..Thai style to built with many people who want to fill pockets but don't want/can work 
Link to comment
Share on other sites

5 hours ago, webfact said:

The construction of the Rama II Road expressway, currently plagued by delays, substandard work and safety concerns, has prompted Prime Minister Srettha Thavisin to consider downgrading contractors responsible for the project. The state budget office was instructed to investigate possible penalties for the contractors involved

Ohhh dear.

Link to comment
Share on other sites

I understand the complaints and criticism, however in my view a 6 month delay on a project this size and complexity is surely reasonable. I drive the road frequently and there are delays on occasions; I'm retired here so a precious extra 30 minutes doesn't phase me.

 

Maybe it's because I come rom the UK. Only 20% of income paid by the motorist in taxes  is used for road infrastructure. The roads are ill maintained and the largest project in the last few years was to turn the emergency breakdown lane of the motorways into a 'part time' extra lane. This grand ides resulted in many deaths . At least Thailand is planning ahead with this scheme whereas the motorist in the Uk is constantly persecuted with surveillance at every road junction, excessive parking fees and extra taxes to enter certain areas of a city in the name of 'combatting climate change'. Oh I almost forgot, we get to benefit from this despite 70 baht/litre. 

Link to comment
Share on other sites

10 hours ago, webfact said:

currently plagued by delays, substandard work and safety concerns

The Contractor the blame for this. 

He's in charge off the Sub contractors he Hired  to do the job.

He's responsible for the Whole project No Excuse.

It' all about money they all are trying to do the job as cheap as possible  they don't care about Safety or Substandard work or substandard materials that are used to make more money

  • Like 1
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...