image.png

 

PATTAYA:--Traffic delays caused by construction will continue for another month on Soi Buakhao as workers install new pumps, flood basin and electric transformer.

 

Contractor Proper Solution Co. began working on the reinforced-concrete flood culvert in November. Two pumps also are being installed, along with a transformer and electric meter.

 

Jirawat Plukjai, president of the Chumsai Community, said the project plan had to be changed because workers hit groundwater about four meters deep. So the basin is now being made wider instead of deeper.

 

Central Pattaya residents have complained about Soi Buakhao frequently being closed during construction, something that’s not about to change. The project is slated to run through May 22.

 

-- PATTAYA MAIL 2019-04-06--

Posted
2 hours ago, Kim J said:

Where is this water going to be pumped to? I can not help but think this project will turn into yet another debacle.

If the contractor was British Rail I am sure next time the Soi floods they would blame it on the wrong type of rain.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...