Land clearing plans for HCMC’s second metro line stuck in limbo


Recommended Posts

Posted

metro2081597892461525215999508-7896-9854-1641526689_680x408.jpg

A land area in HCMC's Tan Binh District has been cleared for a station of the Ben Thanh-Tham Luong metro line. Photo by VnExpress/Huu Khoa

 

Unapproved land price coefficient for HCMC’s District 3 and issues regarding relocation compensation have left plans to clear the land for the city’s second metro line to gather dust.

 

The Management Authority for Urban Railways (MAUR), the Ben Thanh-Tham Luong metro line’s main investor, on Thursday said the land clearing percentage for the line is just 83 percent. The line runs through Districts 1, 3, 10, 12, Tan Binh and Tan Phu, requiring over 251,000 square meters of land to be cleared. Compensation and relocation fees for affected people are estimated at over VND4.35 trillion ($191.4 million).

 

By the end of 2021, out of 603 cases to be relocated due to land clearing, around 50 have yet to be compensated due to multiple issues, including legal procedures and compensation disagreements.

 

Full Story: https://e.vnexpress.net/news/news/land-clearing-plans-for-hcmc-s-second-metro-line-stuck-in-limbo-4413329.html

 

vne_international.jpg
-- © Copyright VN Express 2022-01-07

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...