Phuket Town Cable Burying On Hold For Vegetarian Festival


Recommended Posts

Posted

Phuket Town cable burying on hold for Vegetarian Festival

phuket-1-11046vIgBGqFhZWQAkPbGLNNOqUSpJt.jpg

An excavator sits idle near a mound of dirt as work on burying the overhead cables in Old Phuket Town comes to a halt. Photo: Warisa Temram.

phuket-4-11046ZdCtLgNPHeYgWJZTEpPQRyMNUV.jpg

When the project is complete, the Standard Chartered Bank intersection in Phuket will be free of unsightly cables. Photo: Pimwara Choksakulpan.

PHUKET: Work installing underground utility cables in Old Phuket Town has been suspended for the duration of nine-day Vegetarian Festival, which starts with the arrival of the new moon tomorrow.

“There will be many processions along the streets of the Old Town. The traffic jams would be a nightmare if they continued working while the annual festival was going on,” said Phuket City Mayor Somjai Suwansupana.

Work will resume immediately after the festival, she said.

“Work on the power cables along Krabi Road will resume October 7. That part of the project should take one month. Later, conduit boxes will be installed, which should take another month. Krabi Road will be completed by December,” said Mayor Somjai.

The work is the second of a three-phase effort to beautify the old quarter and increase its attractiveness to tourists.

Phase two is budgeted to cost 39,740,900 baht, comprising 26,476,600 baht from the Provincial Electricity Authority (PEA) and 13,264,300 from Phuket City Municipality.

Work along the selected parts of the more heavily trafficked Thepkrasattri Road and Phuket Road would be a little more complicated.

“The high-voltage cables there are more difficult to work with than regular cables, but we are trying to work as fast as we can in order to minimize the effect on traffic and local businesses in the area,” explained Mayor Somjai.

Work along on Dibuk Road, scheduled to recommence on October 23, targeted for completion by the end of December.

“We started excavation work in June. The work on Dibuk Road will be very much like what we did along Thalang Road,” Ms Somjai said.

The project has suffered other delays, pushing the scheduled completion date for the entire project from this coming December back to March 2012, she said.

“We had some problems with residents in the area. Some of them didn’t understand the project, so I asked the relevant agencies to explain to them in detail what is going on.

“We also had some problems sourcing the cables, as some of the equipment needed to be imported. But all of the problems have been solved,” Mayor Somjai said.

“As soon as we have completed the entire project, we will cut off the power in all the overhead cables and switch it on in the underground cables. Then we will remove all the poles and repave the road, making the whole area ‘wireless’,” she added.

Source: http://www.phuketgazette.net/archives/articles/2011/article11046.html

pglogo.jpg

-- Phuket Gazette 2011-09-26

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...