Jump to content

Heathrow CEO Slept Through Major Power Outage as Phone Was on Silent


Recommended Posts

Posted
7 hours ago, Social Media said:

image.png

 

Heathrow CEO Slept Through Major Power Outage as Phone Was on Silent

 

Thomas Woldbye, chief executive of Heathrow Airport, remained asleep for the first seven hours of a major power outage that paralyzed Europe’s busiest airport because his mobile phone had switched to silent mode without his knowledge. According to an internal review led by former transport secretary Ruth Kelly, fellow Heathrow executives were unable to reach Woldbye after a fire at a substation caused a massive blackout on March 21, grounding thousands of flights and stranding an estimated 200,000 passengers.

 

The incident began at around 11:55pm, but Woldbye, who earned £3.2 million last year, was unaware of the unfolding crisis until approximately 6:45am the following morning. During this critical period, Heathrow’s Chief Operating Officer, Javier Echave, repeatedly attempted to reach Woldbye and ultimately assumed leadership of the emergency response. Echave chaired crisis meetings and made the decision to close the airport for the remainder of the day.

 

The report clarifies earlier claims that Woldbye had knowingly gone to bed after learning about the outage. Instead, Kelly stated that the CEO was unaware of the incident and “expressed to us his deep regret at not being contactable during the night of the incident.” The review has since recommended that Heathrow adopt a dual notification system to ensure key individuals can be reached during significant emergencies. The airport has already taken steps to ensure that its chief executive can be contacted through alternative means in the future.

 

The blackout stemmed from a fire at the North Hyde substation in Hayes, West London, which destroyed both the primary and backup systems. It was later revealed that the fire originated in a 57-year-old transformer and spread to an adjacent unit. A third, newer transformer then overloaded and cut out, severing one of the three main grid lines powering Heathrow. The National Energy System Operator called the event an “unprecedented” failure.

 

Critics from within the aviation industry questioned how such a catastrophic failure could result from the loss of a single substation. Shai Weiss, CEO of Virgin Atlantic, voiced strong disapproval of Woldbye’s absence during the initial response, saying, “I know what I would have done. I would have rushed to the airport at that moment. All CEOs are geared for that. You lead from the front and then you delegate back. I believe if Thomas had the opportunity again he would act differently, but that’s a question for him.”

 

Kelly’s review acknowledged that Heathrow staff responded effectively given the circumstances, managing to restore power later that day by reconfiguring the airport’s internal network. However, it also highlighted a significant vulnerability: while the loss of one grid line was deemed unlikely, staff had been reassured about the substation’s redundancy. Yet, it was known that such a failure would lead to at least an eight-hour shutdown. “This is a result of the way the infrastructure at the airport has been developed over 75 years,” the review noted, pointing out that immediate fixes are unlikely due to limited overnight maintenance windows and spatial constraints.

 

Heathrow has explored various upgrades in the past, including a ring configuration for its high voltage network and a direct connection to the national transmission grid. However, these projects were tied to long-delayed expansion plans, and National Grid has indicated that a direct line may not be possible before 2037.

 

Heathrow chairman Lord Deighton thanked the review committee for their work, stating, “This was an unprecedented set of circumstances, but the learnings identified in the Kelly Review will make Heathrow more fit for the future.”

 

image.png  Adapted by ASEAN Now from The Telegraph  2025-05-30

 

 

newsletter-banner-1.png

Is he not entitled to sleep?

 

There is always a deputy on duty 24/7/365 who is awake for his shift and it is HIS job to sort out the problem. That is why he gets paid a lot of money.

Posted
7 hours ago, Social Media said:

image.png

 

Heathrow CEO Slept Through Major Power Outage as Phone Was on Silent

 

Thomas Woldbye, chief executive of Heathrow Airport, remained asleep for the first seven hours of a major power outage that paralyzed Europe’s busiest airport because his mobile phone had switched to silent mode without his knowledge. According to an internal review led by former transport secretary Ruth Kelly, fellow Heathrow executives were unable to reach Woldbye after a fire at a substation caused a massive blackout on March 21, grounding thousands of flights and stranding an estimated 200,000 passengers.

 

The incident began at around 11:55pm, but Woldbye, who earned £3.2 million last year, was unaware of the unfolding crisis until approximately 6:45am the following morning. During this critical period, Heathrow’s Chief Operating Officer, Javier Echave, repeatedly attempted to reach Woldbye and ultimately assumed leadership of the emergency response. Echave chaired crisis meetings and made the decision to close the airport for the remainder of the day.

 

The report clarifies earlier claims that Woldbye had knowingly gone to bed after learning about the outage. Instead, Kelly stated that the CEO was unaware of the incident and “expressed to us his deep regret at not being contactable during the night of the incident.” The review has since recommended that Heathrow adopt a dual notification system to ensure key individuals can be reached during significant emergencies. The airport has already taken steps to ensure that its chief executive can be contacted through alternative means in the future.

 

The blackout stemmed from a fire at the North Hyde substation in Hayes, West London, which destroyed both the primary and backup systems. It was later revealed that the fire originated in a 57-year-old transformer and spread to an adjacent unit. A third, newer transformer then overloaded and cut out, severing one of the three main grid lines powering Heathrow. The National Energy System Operator called the event an “unprecedented” failure.

 

Critics from within the aviation industry questioned how such a catastrophic failure could result from the loss of a single substation. Shai Weiss, CEO of Virgin Atlantic, voiced strong disapproval of Woldbye’s absence during the initial response, saying, “I know what I would have done. I would have rushed to the airport at that moment. All CEOs are geared for that. You lead from the front and then you delegate back. I believe if Thomas had the opportunity again he would act differently, but that’s a question for him.”

 

Kelly’s review acknowledged that Heathrow staff responded effectively given the circumstances, managing to restore power later that day by reconfiguring the airport’s internal network. However, it also highlighted a significant vulnerability: while the loss of one grid line was deemed unlikely, staff had been reassured about the substation’s redundancy. Yet, it was known that such a failure would lead to at least an eight-hour shutdown. “This is a result of the way the infrastructure at the airport has been developed over 75 years,” the review noted, pointing out that immediate fixes are unlikely due to limited overnight maintenance windows and spatial constraints.

 

Heathrow has explored various upgrades in the past, including a ring configuration for its high voltage network and a direct connection to the national transmission grid. However, these projects were tied to long-delayed expansion plans, and National Grid has indicated that a direct line may not be possible before 2037.

 

Heathrow chairman Lord Deighton thanked the review committee for their work, stating, “This was an unprecedented set of circumstances, but the learnings identified in the Kelly Review will make Heathrow more fit for the future.”

 

image.png  Adapted by ASEAN Now from The Telegraph  2025-05-30

 

 

newsletter-banner-1.png

when i was a CEO in Australia i had 2 phones ,one to home and one to my mistress 

  • Haha 1
Posted
4 minutes ago, portisaacozzy said:

when i was a CEO in Australia i had 2 phones ,one to home and one to my mistress 

 

 

A strategy that was no doubt learned from Pattaya bar girls.

 

 

How many phones did the mistress have?

  • Haha 1
Posted
3 hours ago, JAG said:

This fellow earns £3 million +, phone being on silent is a totally unacceptable excuse!

 

Suck it up buttercup.

 

Woldsys in the club and you ain't!

 

But why is he wearing a bulletproof vest in the picture?

Posted
8 hours ago, Social Media said:

Critics from within the aviation industry questioned how such a catastrophic failure could result from the loss of a single substation.

This is the real problem.

 

The CEO sleeping at night with his phone on silent has zero impact on the root causes of this obvious design flaw.

 

 

Posted
3 hours ago, johng said:

Should also have a landline  or even a direct line that only close colleagues could call..?

Landmine would have been even better.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...