Jump to content

Recommended Posts

Posted
On 9/1/2023 at 11:51 PM, jacko45k said:

It might well be even prettier today as we got a good dose of rain yesterday. 

If it gets much boggier than it currently is they'll probably build another international airport on it ????

  • Haha 2
Posted

Drove around yesterday, they are digging 2nd road up again to lay cables, beach road being repaved and dug up, nightmare

  • Sad 1
Posted
2 minutes ago, Seppius said:

beach road being repaved and dug up, nightmare

+1

That was my observations yesterday as well. In the street, not sidewalk pavement as we know might be finish this year.

Numerous huge orange detour blocks, many many places down beach road.

Not even laughable anymore.

  • Like 1
  • Sad 1
Posted
13 hours ago, Seppius said:

Drove around yesterday, they are digging 2nd road up again to lay cables, beach road being repaved and dug up, nightmare

And soi 15 between 2nd and Buakhao.......never forget that major effort, or lack of. 

  • Like 1
  • Sad 1
Posted
2 hours ago, CRUNCHER said:

Any improvement in the situation to day?

I was there twice today and it's still a nightmare.  Major upgrades take time, not much can be done about it.  

  • Sad 1
  • Thanks 1
Posted
12 hours ago, Bobthegimp said:

I was there twice today and it's still a nightmare.  Major upgrades take time, not much can be done about it.  

Yes I saw a recent post of pics that warned me to stay clear.... 

  • Like 1
  • Sad 1
Posted

Aaaaargh!  saw a couple of youtubers cycle through boomerang and it looked almost finished from Tums massage down to The Avenue... guess I've got another 8 weeks so ill play it by ear, as it could all change again 

 

and there's me still planning on downsizing in the UK and making a permanent move out there!  I'll tell myself its part of Pattayas 'character' ????

  • Like 1
Posted
On 9/2/2023 at 9:40 AM, Shop mak said:

 

 

Beach road footpath walkway is supposed to be finished before high season supposed to start in october 'so they said'. I guess they got both things wrong. Time will tell.

 

 

No the reference to the beach that is supposed to be finished by October is the paving of Beach Rd. In case you have not seen the beach walkway project, it's about halfway done. No way Norway done by October. 

  • Like 2
Posted
On 9/5/2023 at 4:40 PM, Seppius said:

Drove around yesterday, they are digging 2nd road up again to lay cables, beach road being repaved and dug up, nightmare

Right cables on one side pipes on other. Never ever seen such an endless roadworks***show  here. 

Even the sidewalks. As side example things have to be done over and over again. 

  • Like 2
  • Sad 1
Posted

Theppasit road seems like nearly done, but the U-turns are deadly, very small one if you are going towards Sukhumvit and you want to go to Lotus

  • Like 1
Posted
14 hours ago, scubascuba3 said:

Soi 15 fully open now, from Buakhao, also from 2nd road looks finished although I've not ridden all the way through

Might give it a buzz Sunday then..... well done getting this job completed.... thankfully the latter parts were executed better than the initial construction which just seemed to get nowhere for months on end. I guess this is meant to take water from the frequently flooded Buakhao low lying area, to the main system on 2nd Rd? 

  • Like 1
Posted (edited)

Wow, they've even put dashed white lines down the middle and solid yellow line on corners ????

 

Actually it's pretty impressive painting. No sooner do they paint the lines people are riding and walking over them and no marks. Must be instant dry?

 

Edited by Pattaya57

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.



×
×
  • Create New...